Art, Architecture & Design

Site updates and photography by Dave Prichard

Staff have been moving in over the past few days. Everyone is in agreement that the building is looking fantastic. These images were taken on 27 August.

LSAD_DSC0640 LSAD_DSC0658 LSAD_DSC0618 LSAD_DSC0621 LSAD_DSC0629

We are delighted to announce that the AAD Building Extension is now open to staff. Academic and support staff will begin to move into the new facilities from today.

Below (images taken on 21 August) are photographs of the finished rooms with boxes ready to be unpacked ready for the start of the new academic year.

DSC_3232 DSC_3237 DSC_3240 DSC_3241

There are a few bits and pieces left to finish across the building (snagging etc) but the major works programme has officially been completed. As you can see, the external shots of the building look fantastic.

DSC_3250 DSC_3229 DSC_3228

By the start of term, the rooms will be fully completed and ready for use. Below are some additional images from around the building.

DSC_3248 DSC_3246 DSC_3244 DSC_3242 DSC_3238

Most of the rooms on the Ground Floor and First Floor now have crates with equipment ready to be placed. The Second Floor and Third Floor are currently being completed with the finishing touches being put in place (images taken on 15 August). 

DSC_2869 DSC_2883 DSC_2885 

The building is really taking shape now and some of the views are really spectacular across the city.

DSC_2882 DSC_2877

Just a quick update this week to show you some of the areas now waiting for equipment to be moved in (images taken on 7 August).

Below you can see the Fine Art area on the ground floor which will be a great new space to work in. It will connect to MA Fine Art via a door at the far end (shown in the image below).

DSC_2830

Other areas are also progressing well, with the first floor nearly completely finished. It will soon be ready for staff to begin the moving-in process and ICT to begin their installation of computers, screens and networks.

DSC_2832 DSC_2834

The image below shows the Gallery space on the ground floor.

DSC_2831

The roof terrace is truly looking fantastic. Staff and students are going to adore the Cathedral views and open space. There is just a final set of paving to add and then this area will be complete.

DSC_2835

Progress on the finishing and fit out of the building continues apace. The following images were taken on 1 August.

The brickwork is virtually complete, with just a few finishing touches to go.

DSC_2751

This is the roof terrace, as you can see the paving is also nearly complete.

DSC_2770

Inside, the fit out of work spaces is really beginning to make a difference to how the building feels when you walk through it. These image shows the ceramic workshops and conservation areas.

DSC_2766 DSC_2763 DSC_2762

The space for Fine Art on the ground floor is still being used by the construction company as storage whilst the works in the rest of the building are being completed, but you can see from these images, the room will be fantastic to work in.

DSC_2753

DSC_2752b

Below are some other features of the ground floor and first floor including lighting and kitchen fit out.

DSC_2757 DSC_2758 DSC_2754 DSC_2756

On 26 July, Professor Ieuan Owen placed one of the final bricks in the building to commemorate the construction phase drawing to a close.

The image below shows Ieuan cementing in the highest brick or apex of the building (images taken by Elizabeth Mitchell).

DSC_0618

 

With Ieuan in the image below are University of Lincoln Project Managers Peter Harrison (left) and Kevin MacDonald (right).

DSC_0622

The image below shows the view taken from the LPAC – it specifically shows how high the building reaches! (image taken by Dave Prichard)

DSC_2669

It’s getting very exciting on site, the scaffolding is mainly down, leaving just one side and a couple of edges with elevated brick-work to complete (images taken on 18 July). Now that the scaffolding stage is finishing, our stunning new building is being revealed.

DSC_2618 DSC_2619

Additional brickwork on the ground floor will be completed in the final stages of the exterior work. The view across to the Main Administration Building is shown below.

DSC_2628

The image below shows the work to remove scaffolding from the site.

DSC_2620

Work to finish the first and ground floors is well under way. The images below show that the paintwork is complete, electrics and lights are fitted, and now the clean-up operation has started.

DSC_2622 DSC_2623 DSC_2627

The Ground Floor and First Floor are now looking near completion, with finishing taking place on skirting, flooring and walls. These images were taken on 10 July. The below images show the new innovative heating system (ceiling mounted), the fitted toilets and the floors being finished:

DSC_2511 DSC_2515 DSC_2520 

The lift has also seen some significant change, below you can see the walls and ceiling being fitted now the gearing is in place.

DSC_2518

The images below show teaching spaces on the Ground Floor and First Floor. The last image shows one of the academic office spaces.

DSC_2510 DSC_2526 DSC_2527 DSC_2521

The outer wall scaffolding is also staring to come down!

DSC_2509

Last, but not least, some images of the tools and equipment strewn across the building as the rooms near completion.

DSC_2523 DSC_2524

The building works are really beginning to look near completion in many areas. Below (images taken on 5 July) are the exterior shots showing the brick work reaching the fourth floor!

DSC_2374 DSC_2373 #

These shots show the west side also near completion, with the final glazing now going in. Below the scaffolding is the terrace which has spectacular views over the Brayford Pool.

DSC_2412

DSC_2408

Internally, the ground and first floors are also entering the final stages of completion with fixtures and fittings mostly finished.

DSC_2389 DSC_2387 DSC_2383

Significant work has also taken place to install the lift. Below you can see the rigging.

DSC_2378 DSC_2388

And finally, here are some additional images from around the site.

DSC_2375

DSC_2391 DSC_2390 DSC_2379 DSC_2380

The tours for academic staff have continued this week. So far staff have been genuinely delighted at the new learning spaces in the building. These images were taken on 27 June. The images below show the external brickwork on the south side of the building. As you can see the work is really gathering pace now.

DSC_2235 DSC_2236

As you walk into the building, the connection pathway between the existing AAD building and the new one will be full of light and will lead to the reception area.

DSC_2242 DSC_2241

As you move up the floors, the finish becomes more pronounced.

DSC_2244 DSC_2249

My favourite space has to be the roof, with commanding views over the Brayford Pool and Cathedral. The opposite side views down Tritton Road. The space will connect to the existing AAD building. It is quite simply, amazing.

DSC_2255 DSC_2254

 

The third floor is now at the stage where lighting and wiring are going in.

DSC_2259 DSC_2257

And the last image shows the operational heart of the building. Located at the top floor is the equipment that will ventilate and heat the floors below.

DSC_2263

The images below were taken on 21 June. Academic staff from Fine Art and Conservation took a tour of the new building today to see the facilities as they develop. Most of the work is now complete for the space Fine Art and Conservation will be using, with doors, heating, lightning and air conditioning all fitted. We’ll bring you images of all the new teaching spaces in the next few weeks.

DSC_2208 DSC_2217 DSC_2216 DSC_2205

The images below were taken on 13 June.

As you can see, the external walls are going up very quickly, especially on the West side.

DSC_2149 DSC_2177

Internal work still continues apace, with the ground floor nearing completion. Work to add lighting and data cabling is nearing complete here.

DSC_2166

Work continues on each floor, with venting, heating, lighting and cabling work all taking place.

DSC_2160

DSC_2174DSC_2154 DSC_2165 DSC_2164 DSC_2162 DSC_2175

 

The images below were taken on 6 June.

DSC_2030

Brickwork continues to dominate the activity outside of the building, with significant progress being made over the past week.

DSC_2033

This will be the corridor that connects the two halves of the extended building.

DSC_2036

Glazing works have now started, with glass replacing the perspex that was weather proofing the building.

DSC_2039

This is an image of the lift shaft.

DSC_2040

First Floor.

DSC_2049

The roof terrace is already looking amazing, with views casting across the city.

DSC_2052

Floor two.

DSC_2053

Walls being prepared.

DSC_2058

I love these tubes and the effect of texture.

DSC_2061

Work continues to progress well. The images below were taken on 31 May.

DSC_1986

As you can see above, the brick work is going up at most levels.

DSC_2015

The data cables are extensive – ICT will use these to create the network connections around the building.

DSC_2019

An image of the internal staircase.

DSC_2018

An image from the first floor with exposed beams and cabling ready.

DSC_2012

The roof terrace.

DSC_2004

Even more cables!

DSC_1993

This will be the Reception area!

DSC_1988

Work on the glazing is now taking place.

DSC_1987 DSC_1990

Already the building is taking shape internally, with lighting fixtures and doors being added to the ground floor and first floor rooms. Much of the wiring and ducting is complete and the roof terrace is looking spectacular. The second image below shows the room which will connect the new building to the existing building – the light is amazing! Images taken on 24 May.

DSC_1938 DSC_1958 DSC_1955 DSC_1953 DSC_1952 DSC_1948 DSC_1950 DSC_1944 DSC_1943

This week, we have images showing the new door frames and progress of the internal finish. The exterior finish is also really beginning to take shape now. These images were taken on 14 May.

DSC_1817 DSC_1819 DSC_1825DSC_1829DSC_1826

There’s been plenty going on over the past week, with the internal fit progressing well. Below are the progress shots taken on 8 May.

DSC_1671 DSC_1673 DSC_1674 DSC_1679 DSC_1687 DSC_1690 DSC_1692 DSC_1695 DSC_1697 DSC_1698 DSC_1701

With more than 80 workers on site at any one time, there has been good progress on the building since the last update. Brickwork is continuing to go up on all sides and the internal fit out is progressing well. The images below also show paving to sculpture terrace about to be laid (26 April).

DSC_1531 DSC_1541 DSC_1547 DSC_1556 DSC_1562 DSC_1571 DSC_1577 DSC_1584

We’ve got some shots of the inside to share with you! (taken on 23 April):

ADinside

Work on the exterior walls continues this week, with the outer brick work shown below (pictures taken on 15 April):

DSC_1313 DSC_1309

We are really beginning to see the changes in the build project now. The white ‘walls’ are the insulation, and the the buildings are now filling in the bricks either side.

Once we have more access, we’ll begin to take some interior shots so you can see the rooms  being constructed inside.

These images were taken on 5 April.

DSC_1235 DSC_1238

_____________________________________________________________________________

Here are the latest photos for the new AAD Building taken on 21 March.

The walls are going up!

DSC_0968 DSC_0970

DSC_0985 DSC_0966

DSC_0981 DSC_0984

_____________________________________________________________________________

Many thanks to Custard Banjo for these beautiful images. You can follow his Daily Image gallery at http://pinterest.com/unilincoln/daily-iphone-fix/ (15 February)

e1ac27fd247d7c81dd57c73031c751ee defa85d8481cc429c375bb4990590617

Looks like the walls are now taking shape! (taken on 14 February)

DSC_1255

_____________________________________________________________________________

New Hoarding is going up! (images taken on 6 February 2013).

Hoardings 2 Hoardings 1

_____________________________________________________________________________

The latest images shows the walls are now being built! (image taken on 5 February 2013).

DSC_1246

_____________________________________________________________________________

The Building is really taking shape now, with the main structure now in place (images taken on 3 January 2013).

DSC_0745 DSC_0747

Here’s the latest images of the new AAD Building (taken on 14 December)

DSC_0730  DSC_0734

_____________________________________________________________________________

 

The extension to the AAD Building will offer significant investment in improving facilities for Art and Design students on Brayford Campus.

Part of the University’s Estates Masterplan, the vision for the building will be to unite courses taught within the Cathedral Campus to those at the main Brayford Campus. The Building is due for completion in July 2013 with staff and students moving from Thomas Parker House, Greenstone, Think Tank and Chad Varah to AAD.

This blog will track the progress of the multi-million pound building as it is built.

The Building foundation and structure is taking shape with more work to finish the skeleton due to be completed soon.

Existing facilities within the current AAD building have been refurbished for students studying Contemporary Lens Media, Fashion and Product Design. They are due to begin studying on Brayford Campus from January 2013.

Rooms are having new lighting and flooring added ready for January.

The refurbished Gallery will offer a huge space for study.

9 thoughts on “Art, Architecture & Design

  1. Pingback: New and Improved Learning & Teaching Spaces for 2013/14 | Learning Landscapes

  2. Pingback: This page has moved. | Learning Landscapes

  3. Pingback: Art & Design and Library 1.5 pages updated | Learning Landscapes

  4. Pingback: Art & Design and Library 1.5 pages updated | Learning Landscapes

  5. Pingback: The home stretch: Art & Design update | Learning Landscapes

  6. Pingback: | Learning Landscapes

  7. Pingback: Art & Design and summer works update | Learning Landscapes

  8. Pingback: Use the AAD building? New room numbers are being introducing

  9. Pingback: Atrium, AAD and Jackson updates | Learning Landscapes

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>